Wendell Landfill Immediate Response Action
Maxymillian Technologies (MT) mobilized to the Wendell Landfill Site to
perform emergency response action remediation services for the MA DEP.
The landfill's steep embankments, consisting of a wide variety of
demolition debris, were reported to be sliding from the 8-acre landfill
boundaries towards nearby railroad tracks and a river at a rate of 2-3
inches a day. The landfill's highest elevation was 550 feet, greater
than 40 feet above the 508-foot approved construction height. MT
coordinated closely with MA DEP Wetlands Specialists and officials to
apply several innovative and practical control measures and
stabilization techniques.
MT employed their largest capacity equipment and a
majority of their most experienced operators and personnel to complete
the highly accelerated schedule. MT first used dozers to cut access
roads throughout the site that consisted of 4-8" stone for maximum
stabilization and drainage. After road installation, MT mobilized
excavators with up to 72 feet of reach and a fleet of 35 yard Rough
terrain trucks to transfer material to new storage cells at a high
rate. MT moved tens of thousands of cubic yards of material, requiring
thousands of truckloads.
MT placed extensive storm-water management controls to
address the highly sensitive landfill conditions. In response to
site-specific runoff problems on the north side of the site, MT
installed a sediment catching wall specially designed by DEP. This
economical water filtration solution consisted of several rock layers
that filtered runoff destined for the Miller's Falls River below. In
addition, MT constructed two sedimentation and leaching catch basins to
collect runoff. The water basins were lined and divided by stone check
dams that served as filters for water leaving the site.
MT also implemented numerous stabilization measures. On
the south face, MT installed filter fabric to prevent the fragile banks
from erosion resulting from weather conditions. On the rapidly
deteriorating vertical north face, MT installed a manhole and steel
plate system to allow continued collection of leachate from the
landfill. On the east face, the banks were found to be 1 to 1
horizontal to vertical ratio; much steeper than the allowable 3 to 1
ratio under MA regulations. MT implemented stone water channels, pipes,
waterways and hydro seeding to prevent erosion and deterioration of
this bank.
MT placed a high priority on health and safety throughout
all operations. The full time Health and Safety Officer conducted
regular air monitoring. MT consistently applied dust control measures
to protect workers and the surrounding community. Water was also
accessible via pumps to all areas of the site in the event of fire.
MT's highly reliable Site Support Services Team cooperated at great
lengths to complete the remedial response for the MA DEP in the fast
tracked- six month schedule.
- Client: MA Department of Environmental Protection
- Consulting Engineer: IT Corporation
- Location: Wendell, MA
- Project Manager: Paul E. Laviolette
back to Experience
|
|
Long boom excavators recovering material from collapsed landfill slopes.
|