Storm Sewer Line and Manhole Remediation
Maxymillian Technologies (MT) used tunnel jacking techniques that were
successfully employed at the GE Schenectady Facility, to thoroughly
decontaminate a 48" diameter storm sewer pipe and associated manholes
in the High Yard Area. Primary site activities in MT's responsibility
included, removing PCB contaminated sediments, repairing an unknown box
structure, and treating water resulting from storm sewer operations.
Prior to commencing sediment removal, MT conducted site
preparation and established confined space safety and air quality
measures. Throughout remediation activities, MT television-inspected
all sewer lines and manholes to ensure appropriate removal and cleaning
operations. The sediment removal, tunnel jacking method involved the
use of a crane over an access point, excavating 110 cy along the pipe
by hand, and loading out materials using a rail and cart system. The
excavation process allowed for removing approximately 50 feet a day,
totaling 14 days for sediment removal. The carts of contaminated
sediments were winched out of the confined area and placed in
containers for GE disposal.
Using the same removal process, MT removed the solidified
material in the manholes by hand, winched it out, and placed the soil
into GE supplied drums. Following excavation, MT flushed the pipes and
manholes with water. Contaminated sewer water was treated in an
on-site, MT designed and operated water treatment system. Discharged
water was transported to GE's water treatment facility.
Upon completing decontamination, MT reset the plates over
manholes, removed temporary structures, decontaminated equipment, and
restored the site to its original condition.
- Client: GE
- Consulting Engineers: C.T. Male Associates
- Location: Schenectady, NY
- Project Manager: Paul E. Laviolette
back to Experience
|
|
Removing sediment from decontaminated conduits.
|