Norwalk MGP Upper Yard Remediation
Maxymillian Technologies (MT) excavated and removed over 8, 200 tons of
subsurface deposits of coal tar and purifier wastes from the upper yard
of this Former MGP. MT implemented regulatory accepted in-situ blending
techniques that allowed MT to blend the hazardous material with
non-contaminated on-site material during excavation operations to meet
the strict disposal requirements. MT also installed a materials
processing area, sheeting and shoring, decontamination stations,
conducted pavement repairs, and water treatment.
MT implemented extensive erosion control measures and
installed a decontamination area, bituminous concrete lip curb,
anti-tracking pad and temporary haul ramp. The temporary haul ramp
along a rip rap slope provided access to the materials preparation area
and allowed MT to maintain a steady flow of material to and from the
site excavations.
MT performed in-situ blending in 3-5 foot lifts using a
backhoe to make the soil contaminant concentrations uniform. The soil
was then tested for total benzene. After receiving certified laboratory
results, along with specific approval by the disposal facility, MT
loaded the waste into trucks for off-site disposal at a licensed
disposal facility. If contaminant concentrations were too high, MT
processed the soil through a crusher/shredder and screen to a 1" minus
size.
MT implemented extensive sheeting and shoring during
excavations. MT installed a 75' diameter by 30' deep gas holder with
concrete compression rings to support the sheeting. MT removed 8,200
tons of PAH and cyanide contaminated soil from within the rings. MT
installed the shoring, completed excavation activities, and trucked
fill from an approved off-site source. MT then removed the shoring and
simultaneously backfilled and compacted the new material, returning the
excavation to original grade.
Maxymillian Technologies also provided a transportable
Water Treatment System that treated the dewatering water from the
excavations and surface run-off. Overall, MT treated approximately
20,000 gallons of contaminated water.
- Client: Confidential
- Consulting Engineers: Atlantic Environmental Services
- Location: Norwalk, CT
- Project Managers: Glenn A. Houle, Vernon D. Palen
back to Experience
|
|
above:
MT designed concrete compression rings instead of steel bracing to
support a deep MGP holder during contaminated soil removal.
below: Processing soils for off-site disposal.
|