Housatonic
River and Riverbank Excavation (GE Bldg. 68)
Maxymillian Technologies (MT) remediated a section of the Housatonic
River located directly adjacent to GE Building 68. In the late 1960's,
a liquid PCB storage tank located in Building 68 collapsed, leaking its
contents onto bank soils and river sediments. In 1996, US EPA issued an
order for the removal of contaminated materials after materials were
determined to contain elevated levels of PCBs.
Remediation activities began with the installation of 900
feet of steel sheeting, both permanent and temporary, 20 feet deep. The
impervious Waterloo sheet pile wall stopped the migration of DNAPL into
the river.
MT then dredged and disposed of off-site, approximately
4,000 cubic yards of river sediment. The areas and volumes addressed
also included 2,000 in situ cy of bank soils in a 500-ft. length of the
riverbank between Building 68 and the Housatonic River. MT excavated
riverbank soils down to the water table, approximately 13 ft. below the
original grade.
All soil removal operations included river sediment
dredging, appropriate sediment stabilization and water diversion, water
collection and on-site water treatment. MT used a 72' long boom
excavator that extended from the riverbank to the center of the river.
Once the contaminated sediment was removed, MT placed
geotextile and clean fill to within 8" of original grade. MT lined the
dredged area with 8" minus rock fill to stabilize the river bottom. MT
then installed vegetative cover in the upper portion of backfilled area
to restore the excavation to its original grade and to prevent soil
erosion.
- Client: General Electric
- Consulting Engineers: Blasland, Bouck & Lee
- Location: Pittsfield, MA
- Project Managers: Chester Trzcinski, Vernon Palen, David Strzepek
back to Experience
|
|
above: MT excavates using long-reach excavator.
below: MT installs steel cofferdams in Housatonic River before excavating contaminants.
|