Concord Pond Wetlands Cover Construction
Maxymillian Technologies (MT) completed a full-scale forested wetlands
remediation of Concord Pond and its surrounding areas. MT's activities
included installing a storm water discharge drainage, installing
outfall swales and erosion control measures (silt fence, hay bales,
floating booms), excavating, filling, grading, and site restoration.
MT implemented dewatering as-needed throughout the entire
project. MT constructed a dewatering system of a 55-gallon drum filled
with crushed stone and small pump. MT processed any water that required
treatment through carbon vessels and then deposited the water on-site.
MT cleared and grubbed the south side of the site prior
to installing the 8' wide, precast concrete outfall swale. For swale
installation, MT excavated the area to subgrade, placed a 60-mil HDPE
liner, and then placed sand, geotextile, and gravel to grade. After
completing the outfall swale, MT installed the box culvert and
backfilled.
MT then installed a temporary, 4' diameter, corrugated
metal pipe water diversion culvert and a sheeted water diversion
channel. The channel rerouted the water flow towards the temporary
culvert, bypassing the work area. This allowed MT to construct the
peninsula area with pond fill and wetland topsoil. MT protected the
perimeter banks with riprap.
The final installation was a 5' wide precast swale,
layered with Geotextile, crushed gravel, and common fill. MT removed
all temporary measures and restored all construction-disturbed areas
back to their original condition once all construction activities were
complete. After approved and Owner acceptance, MT demobilized from the
site leaving it in a clean and orderly fashion.
- Client: Town of Concord
- Consulting Engineers: QST Environmental (ESE)
- Location: Concord, NH
- Project Managers: Alan N. Steinhoff
back to Experience
|
|
Long-reach excavator is used to trap and remove coal tar contamination without disturbing wetlands.
|